Pre-Shipment Inspection for Industrial and Electrical Goods: A Practical Checklist

How to organise pre-shipment inspections for cables, lighting and industrial equipment: inspection types, AQL sampling, product checks and documents.

Pre-Shipment Inspection for Industrial and Electrical Goods: A Practical Checklist

Finding a problem after goods have arrived in Europe is expensive: return freight, replacement lead times, project delays and sometimes penalties. A pre-shipment inspection (PSI) moves the quality check to the factory, when problems can still be fixed. This checklist explains how to organise one for industrial and electrical products.

Types of inspection

InspectionWhenPurpose
Factory auditBefore the first orderAssess capability, quality system, equipment and certifications
Pre-production checkBefore production startsConfirm raw materials and components match the specification
During-production inspectionTypically at 20–50 % completionCatch systematic defects early
Pre-shipment inspectionWhen production is complete and mostly packedCheck a random sample against agreed criteria
Loading supervisionDuring container or truck loadingVerify quantities, packing and securing

Sampling with AQL

Most inspections use statistical sampling based on ISO 2859-1 (AQL tables). You agree in advance:

  • the inspection level (General Level II is common);
  • acceptable quality limits for critical, major and minor defects (for example 0 / 2.5 / 4.0);
  • what counts as each defect category for your product.

Write these into the purchase order. An inspection without agreed criteria leads to disputes.

Product-specific checks

Cables

  • Sheath printing: type designation, cross-section, voltage, standard, manufacturer and length marking.
  • Dimensions: overall diameter, insulation and sheath thickness on cut samples.
  • Conductor: number and diameter of wires, and a conductor resistance test.
  • Drum labels, lengths and drum condition; CPR labels where applicable.
  • Factory test records (spark test, high-voltage test) for the batch.

See our H07RN-F page for an example of the data you can check against.

Lighting

  • Power consumption and power factor at rated voltage.
  • Light output and colour temperature on a sample (or comparison with a golden sample).
  • Driver brand and model, surge protection and IP sealing.
  • Labelling, CE marking, WEEE symbol and instructions — see our street lighting guide.
  • Function test and burn-in records.

Mechanical and bulk handling parts

  • Dimensions and material against drawings (for example bucket dimensions and thickness for elevator buckets).
  • Material certificates (EN 10204 3.1 where requested).
  • Surface treatment and coating thickness.
  • Fit check with mating parts where possible.

Documents to verify at inspection

  1. Packing list against the order.
  2. Declaration of Conformity, test reports and certificates — see our CE marking checklist.
  3. Origin documents if you claim preferential duty.
  4. Marking and labelling in the required languages.

When goods fail

Agree the process before the inspection: rework and re-inspection at the supplier’s cost, sorting of the lot, or rejection. Photographs and a clear defect list are essential. For recurring problems, ask for a corrective action report and consider a during-production inspection on the next order.

Packing for European delivery

Check that packaging suits the route — sea, road or multimodal — and the receiving site: pallet sizes compatible with European handling (for example 1200 × 800 mm), heat-treated wooden packaging marked to ISPM 15, drum sizes that site equipment can handle, and labels readable by the receiving warehouse.

Wesourcia inspection support

We can organise inspections at our suppliers’ factories and share reports and photos before shipment. Learn more about our sourcing and procurement services or request a quote including your inspection requirements.

Frequently asked questions

What is AQL in inspections?

AQL (acceptable quality limit) sampling, based on ISO 2859-1, defines how many units are inspected and how many defects of each category are allowed before a lot is rejected.

When should a pre-shipment inspection take place?

When production is complete and most goods are packed, so the inspector can draw a random sample from the finished lot before it leaves the factory.

What should be checked on cable drums?

Sheath printing, dimensions, conductor construction and resistance, drum labels and lengths, CPR labels where applicable, and the factory test records for the batch.

Products mentioned in this article

Need a different size, standard or quantity? Request a quote

Have a sourcing question?

Our team can help you specify, source and compare products for your project.